RACI Matrix

Responsibility Assignment Matrix: roles per activity and stakeholder

Anatomy of a RACI Matrix

The RACI matrix clarifies, for every task or activity in a project, who has which role. The four letters stand for four clearly defined types of responsibility. It prevents duplicated work, responsibility gaps, and unclear decision paths.

R — Responsible: Who actually does the work? Multiple people can be "R" per task but should be rare — otherwise responsibility frays.

A — Accountable: Who is ultimately accountable for the result and makes the final decision? Exactly one person per task — not zero, not two. "A" wears the hat, "R" does the work.

C — Consulted: Who is asked for input before the decision? Two-way communication. Typically subject-matter experts whose knowledge is essential but who do not decide.

I — Informed: Who is informed about the result? One-way communication. Stakeholders who need to know the status but have no active role.

Tasks (rows) and people (columns): The matrix lists tasks or deliverables on the left and roles or people across the top. Each cell carries the letter (R/A/C/I) or remains empty if there is no involvement.

Approach

  • List tasks or deliverables from the project plan — as rows.
  • Add involved people or roles as columns.
  • Assign exactly one "A" per task — the final authority.
  • At least one "R" per task — the doing hand.
  • Use "C" sparingly — only when the input is truly needed, otherwise bottlenecks appear.
  • "I" for everyone who needs to know the result without participating in the decision.
  • Review the matrix with the team and get sign-off — resolve conflicts before the project runs.

Pitfalls

Multiple "A" per task: When two people are accountable, no one really is. On conflict nothing escalates, on success both fight for credit. Exactly one "A" per row.

No "A": A task without "A" is no-man's land — it will be left alone or done under wrong assumptions. Every row needs a hat wearer.

Too many "C": Having to consult three experts kills speed. Consultation costs time — only involve the truly necessary, the rest are "I".

Confusing "R" and "A": "R" does the work, "A" is accountable for the result. Often the same person, sometimes deliberately not — e.g. an operator does it, a shift lead is accountable.

Matrix is not lived: A RACI matrix in the drawer helps no one. It should be communicated at project start and updated on every role change.

Column choice: person vs. role: People change, roles are more stable. For long-running projects, prefer roles ("shift lead") to names — otherwise the matrix has to be reworked on every staff change.